A team's done rule requires acceptance checks, tests, review and merge. The checks and tests pass, and review is complete, but merge is pending. Is the issue done?
Which issue is scoped well enough to finish and review?
An estimate guarantees that the work will finish within its range.
Circle one: True False
A new library's behaviour is uncertain. The team's current duration estimate is three to six working days. How should it report the estimate?
An export feature needs CSV and JSON output. Each format can be tested and merged separately. Which split gives each issue a checkable result and separately reviewable changes?
A team planned nine pieces and completed six. Records show the other three waited for review. What should the next planning discussion do?
Two pieces exceeded their estimates: one lost time when a teammate was ill, and one needed unexpected library work. What is a justified response for the next plan?
A manager treats estimates as promises. The team reports doubling its ranges solely to avoid accusations of breaking promises. Scope and effort assumptions have not changed. What does this evidence support?