A team's done rule requires acceptance checks, tests, review and merge. The checks and tests pass, and review is complete, but merge is pending. Is the issue done?
- Done: tests passed
- Done: writing the code is enough without the agreed completion checks
- Not done: the agreed merge step is still pending
Which issue is scoped well enough to finish and review?
- An issue bundling unrelated changes across several future releases
- A scoped issue with a checkable result and reviewable changes
- A short issue title with no defined result
An estimate guarantees that the work will finish within its range.
Circle one: True False
A new library's behaviour is uncertain. The team's current duration estimate is three to six working days. How should it report the estimate?
- A fixed four-day promise, leaving the library uncertainty out of the plan
- No estimate, while assuming the library cannot delay the team's planned work
- Three to six days, with assumptions and a review after a short trial
An export feature needs CSV and JSON output. Each format can be tested and merged separately. Which split gives each issue a checkable result and separately reviewable changes?
- CSV export and JSON export, each with its own checks and review
- UI buttons and backend stubs, with neither issue having a checkable result on its own
- CSV and JSON files mixed across two issues, with each output check requiring both issues together
A team planned nine pieces and completed six. Records show the other three waited for review. What should the next planning discussion do?
- Review the queue and adjust work in progress or review capacity
- Blame the authors and keep the same workload
- Discard the review records and increase planned work without checking capacity
Two pieces exceeded their estimates: one lost time when a teammate was ill, and one needed unexpected library work. What is a justified response for the next plan?
- Review capacity risk and library uncertainty, then revise the plan
- Revise only the library estimate, treating illness as irrelevant to capacity
- Double every estimate permanently, treating both events as recurring delays
A manager treats estimates as promises. The team reports doubling its ranges solely to avoid accusations of breaking promises. Scope and effort assumptions have not changed. What does this evidence support?
- The unchanged scope proves the tasks require twice the original effort
- The team padded ranges to reduce promise pressure
- Doubling estimates proves all future delivery dates will be accurate